What We Need From You Before We Can Quote a Steel Warehouse

A large share of the RFQs we receive say the same thing. We need a warehouse, please send your best price. We can reply to that, but the number will be a placeholder. Two quotations for the same footprint can differ by a wide margin, and neither of them is wrong, because the buildings behind them are different.

Below is the list we go through with every client. Fill these in and the first quotation usually survives to the contract without major changes, which saves you a month of email.

Size: length, width and eave height

Length and width are easy. Eave height is the one that gets skipped, and it matters twice. It decides what you can stack, lift or park inside, and it drives steel tonnage faster than any other single number, because every extra meter of height adds weight to the columns and the roof.

Tell us the clear height you actually need, meaning the free space under the roof beams or the crane, not just the wall height. If a mezzanine is planned, say so now. If a crane is needed, we need the tonnage, the span, the lifting height and roughly how many lifts per hour, because an overhead crane changes the whole frame.

Location and loads

Wind load, snow load and seismic requirements come from the site, not from the building. Give us the city or the exact address and we will check the values. If your engineer already has them from the local code, send the numbers and we will use yours.

Ground conditions decide the foundation. Solid soil and soft filled ground produce very different footing designs, and the foundation is often the second largest cost after the steel. Tell us what you know, and if a soil report exists, send it. Near the coast, tell us that too, because salt air changes the coating specification.

Roof, wall and openings

We need to know whether the roof is single slope or double slope, and which panel system you want. Single steel sheet is the cheapest option and it is fine for unheated storage. Sandwich panel with polyurethane or rock wool gives insulation, and the thickness and core material decide the price and the fire rating.

Then come the openings, which are usually underestimated. Rolling doors, sliding doors, sectional doors, windows, skylights, gutters, downpipes, ventilators. A simple sketch with dimensions on the wall is enough. It does not have to be a CAD drawing.

What goes inside

A warehouse for packed cartons and a warehouse for steel coils are not the same building. Tell us what you store, how it is stacked, and whether racking will be anchored to the floor. If the goods need temperature control, say so, because insulation and ventilation change with it. If there is dust, chemicals or food, there may be fire rating requirements that affect the panels and the steel protection.

Delivery and installation

Give us the discharge port and how the containers will move from the port to the site. A road with a low bridge or a narrow village lane can decide how we pack the members, and repacking later costs more than designing for it once.

Tell us what you want us to do on site as well. Some clients have their own erection crew and only need drawings plus a supervisor for the first days. Some want a full team from us. Some want steel only. All three are possible, and the price is different. If you have a target date, send it with the RFQ rather than after the price is agreed.

A short RFQ you can copy

If you would rather not write a long email, these eight lines are usually enough to start:

1. Project location, city and full site address.

2. Length, width and eave height in meters, and the clear height you need inside.

3. Clear span, and whether an overhead crane is required, with tonnage and lifting height.

4. Roof and wall panel type, or the insulation level you need.

5. Door and window schedule, or a sketch.

6. Local wind load, snow load and seismic data, or just the city so we can check.

7. Ground condition, and whether the foundation is in your scope or ours.

8. Discharge port, site access notes, and the date the building must be finished.

Questions clients ask us

Do you need architectural drawings before quoting? No. A dimensioned sketch and the use of the building are enough to quote and to start the design. The formal drawings can come later, and we will issue them for your approval before fabrication.

Can you design to our local code? Usually yes, if you send us the code name and the load values, or the standard you want us to follow. Where the code is unfamiliar to us, we will say so instead of guessing.

How long does a quotation take? Three to five working days for a standard warehouse once the details above are in hand. Complex frames with cranes or mezzanines take longer, and we will tell you when we receive the RFQ.