This is one of the first questions in most RFQs we receive, and the honest answer is a range, not a date. The range depends on how fast the drawings are approved, how full the workshop is when your order lands, how far the site is from the port, and whether the ground is ready when the trucks arrive.
Here is how the time usually splits, and where it actually goes.
A prefabricated steel building runs on four separate clocks, and they only partly overlap. Design and approval is paperwork plus engineering. Fabrication is workshop capacity. Shipping is a sailing schedule you do not control. Site work is ground, crane and crew.
Table 1. Typical stage durations for an export warehouse of 1,000 to 2,000 square meters, single story, standard panels.
Stage | Main work | Typical duration |
Design and approval | Structural design, layout drawings, connection details, client approval | 1 to 3 weeks, depending on how fast the client replies |
Workshop fabrication | Cutting, welding, drilling, surface preparation, painting, packing | 4 to 6 weeks for 1,000 to 2,000 square meters |
Shipping | Booking, container loading or breakbulk, customs, inland transport | 2 to 6 weeks, depending on route and port |
Foundation and erection | Civil foundation, unloading, lifting, roof and wall panels, flashings | Foundation 2 to 4 weeks, erection 3 to 6 weeks |
Drawing release to handover | The four stages above, partly overlapping | Usually 3 to 5 months in total |
These are the ranges we see on export projects of ordinary size and ordinary complexity. A small shed with standard panels sits at the short end. A building with overhead cranes, mezzanines or unusual geometry sits at the long end, or beyond it. The foundation is the item most often outside our scope, and it is also the item most often late.
In our experience it is rarely the workshop. The common causes are these. Dimensions change after fabrication has started, which means cutting and repainting, and the schedule resets. The foundation is not ready when the first container arrives, so the crew waits on site at daily cost. The crane is booked for a date that does not match the ship. The client’s import paperwork is incomplete when the vessel berths, and storage charges begin.
One more, less obvious. Panels and flashings take longer to install than the frame. Clients plan for the steel erection and forget that the roof closing is what actually protects the building, and it is done by hand, meter by meter.
Freeze the dimensions before fabrication. Every change after that point costs both material and time, and the second cost is larger.
Let the foundation and the fabrication run in parallel. The workshop does not need the site to be ready. This is the single biggest overlap available, and it is often skipped because the client waits for the foundation before placing the order.
Use standard bay spacing and standard panel lengths where the design allows. Custom modules look good on the drawing and add weeks in the workshop.
Ship in the erection sequence. If the columns are buried behind the wall panels in the container, the crew will unload twice.
Book the crane and the crew before the vessel sails, not after it arrives.
Work backwards from that date instead of forwards from today. Subtract the erection, the shipping, the fabrication, the approval. If the sum does not fit the calendar, change the scope before you change the promise. A simpler roof, standard panels and a rectangular footprint can take weeks out of the workshop. Squeezing the erection phase rarely does, because the crew can only work so fast on a given building.
We would rather tell a client in the first week that the date is not achievable than tell them in the fourth month.
Can erection be faster? Yes, with more crews and more crane time, and you pay for both. In practice the frame goes up quickly and the closing details set the pace, so adding people to the frame does not shorten the job much.
Can you ship in phases? Yes, and for a large building it is usually the right answer. We phase the shipment to match the erection sequence, so the site is not used as a warehouse.
What if my site is not ready when the goods arrive? Then the goods wait, either at the port or on your land, and both cost money. It is better to align the dates at the order stage than to solve it at the port.