Solar on a Factory Roof: Six Checks Before We Quote

Oct 30, 2026

Share:

Solar on a Factory Roof: Six Checks Before We Quote

A rooftop solar quotation is easy to produce and easy to get wrong. The panels are a commodity. What separates a system that runs for twenty-five years from one that leaks, rattles or underperforms is almost entirely what happened before the first bracket went on.

These are the six checks we run on every factory roof, in this order.

One: what the roof can carry

Every system adds weight. Panels, rails, clamps and cable trays usually land somewhere between 12 and 18 kilograms per square meter, spread across the roof. On a steel roof that load goes into the purlins, so we need the purlin spacing, the section size and the sheet profile. On a light or old roof, the answer may be to add purlins before adding panels.

Wind matters as much as weight. Uplift at the edges and corners of a roof can be several times the pressure in the middle, so the perimeter rows need more fixings than the centre. A quote that treats the whole roof the same way was written from a drawing, not from the building.

Two: the sheet, the seams and the age

Three roof types behave differently. A trapezoidal steel sheet with clamps needs no drilling, so the waterproofing stays untouched. A standing seam roof is easier still, because the seam gives a continuous line to fix to. A sandwich panel roof works, but the core and the seam detail decide whether a clamp crushes the panel.

Concrete roofs need ballast or anchors, and the membrane has to survive both. If the membrane is near the end of its life, the sensible order is membrane first, solar second. We have seen arrays installed on roofs that were replaced two years later, and removing them was not in anyone's budget.

Three: shading, pitch and row spacing

A factory roof is rarely a clean rectangle. Parapets, skylights, ventilation stacks, crane rails, and on older sites a second building casting a shadow from two o'clock. We map shading through the year, not at noon in June.

Row spacing is a compromise. Tight rows mean more panels per square meter and more shading between rows in winter. Wide rows mean fewer panels and more yield per panel. There is no universal number, and anyone quoting a fixed pitch without asking your latitude is guessing.

Four: where the power goes

The electrical side is where most projects lose time. We need the transformer capacity, the spare breaker positions, the distance from the roof to the inverter and from the inverter to the main board, and a clear answer on whether the utility allows export at all.

In some markets you can export freely. In others you need approval, a bidirectional meter and a protection relay, and the process takes months. In a few, export is not permitted and the system must be sized so that nothing leaves the site. That single rule changes the design more than the roof does.

Five: sizing against the load curve

We ask for twelve months of bills and, if the meter can provide it, a half-hourly load profile. A single shift plant and a three shift plant need very different systems on an identical roof.

The number we watch is self-consumption. If ninety percent of generation is used on site, the saving is the retail tariff. If half of it is exported at a low rate, payback stretches and the project looks worse than it is. Size to the load, then fill the usable roof. That order usually produces the better return.

Six: access, cleaning and who owns the data

Someone has to walk on that roof for twenty-five years. Access hatches, guard rails and anchor points cost money on day one and prevent injuries later.

Dust matters more than people expect, especially near cement plants, quarries and dry inland sites. If the array needs cleaning twice a year, that is a maintenance contract, not a footnote in the brochure.

The monitoring should belong to you. A system that reports into a supplier portal and stops reporting when the service contract ends is a system you cannot troubleshoot.

One thing we will not do

We do not quote a rooftop system without looking at the roof. Photos are enough to start, a site visit is better, and a structural check is required when the building is more than fifteen years old or when the drawings are missing. It costs a day and it protects both sides.

Questions we get

Can you install on a roof we did not buy from you? Yes. We survey it first, and if it was not our structure we ask for the drawings or measure the purlins on site.

Clamps or ballast on a steel roof? Clamps, unless the sheet profile does not allow it. Ballast on a steel roof is heavier and it loads the purlins in a way they were not designed for.

Do we need a battery? Only if your value sits in the evening peak or in backup power. For pure self-consumption during the day, a battery usually lengthens the payback.

Send us the roof drawings, the electricity bills and a note on your shift pattern. We will come back with the six checks above, written out for your building, before any price is discussed.